QuestionQ40
VerifiedManaging the Test ActivitiesYou are the Test Manager for a project that uses a V-model with four formal testing levels: unit, integration, system, and acceptance testing.
On this project, reviews have taken place for every development phase before testing; that is, requirements, functional specification, high-level design, low-level design, and code reviews have been performed before testing.
Assume that no requirements defects were reported after the product release.
Which TWO of the following metrics are needed to evaluate the requirements reviews in terms of phase-containment effectiveness?
Choose two