QuestionQ4

VerifiedManaging the Test Activities

You are estimating the effort required for integration-testing activities in a new project. Consider the following factors, which may affect that estimate:

  1. Availability of reusable test systems and documentation from earlier, similar projects
  2. Unanticipated timing of component arrivals
  3. Stability of the integration test team (no turnover)
  4. Many geographically distributed sub-teams

Which of the following statements is true?

Explanation

Unexpected component arrivals introduce uncertainty into integration-test scheduling and dependencies. Numerous geographically distributed sub-teams increase coordination and communication complexity. Both factors can adversely affect the accuracy of a test-effort estimate, whereas reusable assets and a stable test team generally support more reliable estimation.