You are the Test Manager for a project that follows an iterative life-cycle model. The project is to comprise nine iterations, each lasting one month. The plan is to develop the most important features to establish a stable application core in the first three iterations, then add the additional features in the final six iterations.

At the start of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that, in each of the first three iterations, the selected features are fully completed and unit tested.

Which of the following statements is true in this context?

Explanation

Iterative development calls for testing during each iteration. Because the first three iterations deliver the most important features and establish the stable core of the application, significant system-testing effort is needed in those iterations to test the completed features together and identify integration or system-level defects early.

Community Discussion

No comments yet. Be the first to start the discussion!