VerifiedManaging the Test ActivitiesAssume that you have data on confirmation testing performed during system testing for a previous project.
In that project, 240 bug reports were opened once, 80 were opened twice, 10 were opened three times, and no bug reports were opened more than three times.
You estimate that a bug report that fails its confirmation test costs an average of 3 person-hours.
Which of the following statements correctly describes the value of these confirmation-testing activities in terms of cost of quality?