QuestionQ23

VerifiedManaging the Product

Over the next two months, new features will continually be added to new releases of a project on which you are working as Test Manager.

You have identified a main project risk: the requirements specification will still be incomplete when your team begins the test design and implementation phase. Some requirements will likely be completed too late to permit proper test preparation.

You and your test team have already worked on several similar previous projects in the same organization. Which of the following options would you expect to be most effective in mitigating this risk?

Explanation

Using experience from similar projects to make reasonable assumptions enables test preparation to begin despite incomplete requirements. Lightweight, easily updated tests limit rework when the missing details are finalized, thereby reducing the impact of late requirements on test design and implementation.