QuestionQ11

Managing the Test Activities

Which of these is an example of the test-closure activity called “lessons learned”?

  • A Archive all the test results of the acceptance testing phase
  • B Deliver a list of the open defects of a software product released into production to the service desk team
  • C Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
  • D Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for
Explanation

Lessons learned involves holding a retrospective-style meeting to review events and problems and identify improvements for future projects.