QuestionQ104Verified/Incident Response and RecoveryCopy linkReport a problemAsk AstroTutorSave questionWhich of the following disaster-recovery statements is incorrect?AA recovery team's primary task is to get the pre-defined critical business functions at the alternate backup processing site.BA salvage team's task is to ensure that the primary site returns to normal processing conditions.CThe disaster recovery plan should include how the company will return from the alternate site to the primary site.DWhen returning to the primary site, the most critical applications should be brought back first.Show AnswerAnswerExplanationA salvage team is responsible for salvaging recoverable equipment, media, records, and other assets at the affected site. Returning the primary site to normal operating conditions is a restoration or reconstitution activity, not the salvage team’s task.Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!