QuestionQ235

VerifiedSecure Software Lifecycle Management

Henry is the project manager for his company’s QBG Project. The project has a budget of $4,576,900 and is expected to take 18 months to complete. The CIO, a project stakeholder, has submitted a scope change request for additional deliverables as part of the project work. Which component of the change control system would review the proposed changes’ impact on the features and functions of the project’s product?

Explanation

A configuration management system assesses and controls changes to a product’s functional and physical characteristics, including its features and functions, while maintaining the integrity of the approved product configuration.