Mark is the project manager for the NHQ project at StarTech Inc. The project includes an asset valued at $195,000 and has an exposure factor of 35 percent.

What is the project's Single Loss Expectancy?

  • A $68,250
  • B $92,600
  • C $72,650
  • D $67,250
Explanation

Single Loss Expectancy (SLE) is calculated as asset value multiplied by exposure factor. An asset value of $195,000 with a 35 percent exposure factor produces an SLE of $68,250.