QuestionQ139

VerifiedSecure Software Lifecycle Management

Rob is the project manager for his company’s IDLK Project. The project has a budget of $5,600,000 and is expected to run for 18 months. Rob has learned that a new law could affect how the project may proceed—even though the organization has already invested more than $750,000 in it. What risk response is most appropriate in this situation?

Explanation

Mitigation is used for a threat when the project team takes action to reduce its probability or impact. Preparing for and adapting to a possible legal constraint can limit the effect of the new law on project execution.