QuestionQ2

VerifiedSecurity Assessment and Testing

When auditing the Software Development Life Cycle (SDLC), which of the following is a high-level audit phase?

Explanation

Planning is a high-level audit phase in which the audit scope, objectives, approach, resources, and relevant risks are established. Risk assessment is typically a planning activity, while requirements are an SDLC phase rather than an audit phase.