During the "Do" phase of the Plan-Do-Check-Act model, which of the following activities is performed?

Explanation

The Do phase puts the established business continuity policy, controls, processes, and procedures into operation. Establishing them belongs to Plan, performance monitoring and review belong to Check, and corrective action based on review results belongs to Act.