QuestionQ997

Risk Assessment

You are the project manager for the NHH project. You are working with the project team to examine the project from four defined perspectives, increasing the breadth of identified risks by including internally generated risks. Which risk identification approach are you using in this example?

  • A Root cause analysis
  • B Influence diagramming techniques
  • C SWOT analysis
  • D Assumptions analysis
Explanation

SWOT analysis evaluates strengths, weaknesses, opportunities, and threats. Its strengths and weaknesses perspectives identify internal sources of risk, while opportunities and threats help identify external risks.

Community Discussion

No comments yet. Be the first to start the discussion!