QuestionQ997
Risk AssessmentYou are the project manager for the NHH project. You are working with the project team to examine the project from four defined perspectives, increasing the breadth of identified risks by including internally generated risks. Which risk identification approach are you using in this example?
- A Root cause analysis
- B Influence diagramming techniques
- C SWOT analysis
- D Assumptions analysis