QuestionQ971

Risk Assessment

You are the project manager for the GHT project. You have identified a project risk event that could save $100,000 in project costs if it occurs. Which statement BEST characterizes this risk event?

  • A This risk event should be mitigated to take advantage of the savings.
  • B This is a risk event that should be accepted because the rewards outweigh the threat to the project.
  • C This risk event should be avoided to take full advantage of the potential savings.
  • D This risk event is an opportunity to the project and should be exploited.
Explanation

A possible $100,000 cost saving is a positive risk—an opportunity. Exploiting an opportunity means taking action to ensure that the beneficial event occurs and the project realizes its value.