QuestionQ965

Governance

You have been elected as the project manager for the GHT project and must initiate it. The project request document has been approved, and you now need to begin work on the project. What is the FIRST step you should take to initialize the project?

  • A Conduct a feasibility study
  • B Acquire software
  • C Define requirements of project
  • D Plan project management
Explanation

Project requirements establish the expected scope, deliverables, and constraints. They must be defined at the outset so that subsequent project-management planning is based on what the project is required to achieve.