QuestionQ96

Risk Response and Reporting

Which of the following is the MOST important cost-related objective for considering aggregated risk responses within an organization?

  • A Reduce likelihood
  • B Address more than one risk response
  • C Prioritize risk response options
  • D Reduce impact
Explanation

Aggregating responses can address multiple related risks through a shared control or treatment, reducing duplicated effort and overall response cost.