QuestionQ954

Risk Assessment

Which of these events is MOST likely to prompt an update to the risk register?

  • A A reminder to reassess an identified risk has been sent to risk owners and risk custodians.
  • B A business case for implementing a new solution for automating controls has been proposed.
  • C A project to implement a risk response action plan has been completed and closed successfully.
  • D A post-implementation review of a new application has been initiated by senior management.
Explanation

Completion and successful closure of a project that implements a risk response action plan confirms that a planned treatment has been carried out. The related risk record should be updated to reflect the response status and any resulting residual risk.