Kelly is the project manager for her company’s NNQ Project. The project will run for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to start the risk response planning process. Which two inputs does Kelly need to begin the Plan Risk Responses process?

  • A Risk register and the results of risk analysis
  • B Risk register and the risk response plan
  • C Risk register and power to assign risk responses
  • D Risk register and the risk management plan
Explanation

Plan Risk Responses requires the risk register to identify and prioritize the project risks needing treatment, and the risk management plan to provide the established risk-management approach and criteria. The risk response plan is produced through this work rather than supplied as an input.