QuestionQ926

Risk Response and Reporting

What is the PRIMARY reason for sharing risk assessment reports with senior stakeholders?

  • A To enable senior management to compile a risk profile
  • B To support decision-making for risk response
  • C To secure resourcing for risk treatment efforts
  • D To hold risk owners accountable for risk action plans
Explanation

Risk assessment reports provide senior stakeholders with the information needed to choose and authorize an appropriate response to identified risks, based on their likelihood, impact, and priority.