Fred is the project manager for a large project in his organization. He needs to start planning the risk management plan with the project team and key stakeholders. Which tool and technique for the Plan Risk Management process should Fred use to plan risk management?

  • A Information gathering techniques
  • B Data gathering and representation techniques
  • C Planning meetings and analysis
  • D Variance and trend analysis
Explanation

Planning meetings and analysis bring the project team and key stakeholders together to define the risk-management approach, including how risk activities will be conducted. This aligns the plan with stakeholder expectations and establishes the procedures for managing project risk.