QuestionQ841

Risk Assessment

What term describes a project risk when it appears likely to occur?

  • A Issue
  • B Contingency response
  • C Trigger
  • D Threshold
Explanation

A project risk is an uncertain event or condition. When it materializes as a current or imminent problem requiring attention, it is treated as an issue. A trigger is instead an indicator that a risk event may be imminent.