You are the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan defines who will be available to share information about the project risks?

Explanation

The Communications Management Plan establishes how project information is shared, including who is responsible or available to communicate risk information to stakeholders.