During qualitative risk analysis, you want to define the risk urgency assessment. Which of the following is not an indicator of risk priority?

  • A Warning signs
  • B Symptoms
  • C Risk rating
  • D Cost of the project
Explanation

Risk urgency and priority are assessed using risk-specific indicators, including warning signs, symptoms, and risk rating. The total cost of the project does not indicate the urgency or priority of a particular risk.