QuestionQ740

Risk Assessment

You are the project manager for the ABS project, which is establishing a computer network on school premises. During project execution, school management requests that the campus be made Wi-Fi enabled. You know this could adversely affect the project and have discussed the change request with other stakeholders. What is your NEXT step?

  • A Update project management plan.
  • B Issue a change request.
  • C Analyze the impact.
  • D Update risk management plan.
Explanation

A requested Wi-Fi capability changes the project’s requirements and may affect scope, schedule, cost, resources, and risk. Its impact must be analyzed before project management plans are updated or the change is advanced for approval and implementation.