QuestionQ740
Risk AssessmentYou are the project manager for the ABS project, which is establishing a computer network on school premises. During project execution, school management requests that the campus be made Wi-Fi enabled. You know this could adversely affect the project and have discussed the change request with other stakeholders. What is your NEXT step?
- A Update project management plan.
- B Issue a change request.
- C Analyze the impact.
- D Update risk management plan.