QuestionQ74

VerifiedRisk Assessment

You are the project manager for the HGT project at Bluewell Inc. The project has an asset valued at $125,000 and is subject to an exposure factor of 25 percent.

What is the Single Loss Expectancy for this project?

Explanation

Single Loss Expectancy is calculated as asset value multiplied by exposure factor. An asset value of $125,000 with a 25 percent exposure factor produces an SLE of $31,250.