QuestionQ727

Risk Response and Reporting

Which of the following is the BEST action for a risk practitioner when a project team has accepted a risk that is outside the established risk appetite?

  • A Monitor the residual risk level of the accepted risk.
  • B Escalate the risk decision to the project sponsor for review.
  • C Document the risk decision in the project risk register.
  • D Reject the risk acceptance and require mitigating controls.
Explanation

Risk appetite defines the boundary of risk the organization is willing to accept. Acceptance beyond that boundary is a governance exception that requires review by the accountable sponsor or other authorized escalation authority. Monitoring or recording the decision does not authorize the exception, and a risk practitioner does not ordinarily override the team’s decision unilaterally.

Learn more