QuestionQ727
Risk Response and ReportingWhich of the following is the BEST action for a risk practitioner when a project team has accepted a risk that is outside the established risk appetite?
- A Monitor the residual risk level of the accepted risk.
- B Escalate the risk decision to the project sponsor for review.
- C Document the risk decision in the project risk register.
- D Reject the risk acceptance and require mitigating controls.