QuestionQ701

Risk Assessment

You are a project manager at BlueWell Inc. and are preparing for the risk-identification process. You will need to involve several key project stakeholders to help identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify those risk events.

Which one of the following is NOT a document that will help you identify and communicate risks within the project?

  • A Stakeholder registers
  • B Activity duration estimates
  • C Activity cost estimates
  • D Risk register
Explanation

The risk register is an output of risk identification: it records the risks and their characteristics after they have been identified. Stakeholder registers and activity duration and cost estimates are project documents that can be examined for sources of stakeholder, schedule, and cost risk.