Which of the following would be MOST useful for measuring progress against a risk response action plan?

  • A Resource expenditure against budget
  • B An up-to-date risk register
  • C Percentage of mitigated risk scenarios
  • D Annual loss expectancy (ALE) changes
Explanation

The percentage of mitigated risk scenarios directly indicates how much of the planned risk-response work has been completed and has achieved mitigation. Resource spending, a current risk register, and changes in annual loss expectancy do not by themselves measure progress of the response actions.