You have been assigned as the Project Manager for a new project involving construction of a new roadway from the city airport to a designated point within the city. However, you notice that the transportation permit-issuing authority is taking longer than planned to issue the permit needed to begin construction. How would you classify this?

  • A Project Risk
  • B Status Update
  • C Risk Update
  • D Project Issue
Explanation

A project issue is a current condition or event that has already occurred and requires attention or resolution. The permit authority is already taking longer than planned to issue the construction permit, so the delay is an active project issue rather than an uncertain project risk.