QuestionQ617

Governance

Which three actions are the PRIMARY steps for initializing the project?

Each correct answer represents a complete solution.

Choose three
  • A Conduct a feasibility study
  • B Define requirements
  • C Acquire software
  • D Plan risk management
Explanation

Project initiation evaluates feasibility and defines the business, functional, and technical requirements that establish the proposed system’s scope. When the selected approach is to acquire rather than develop a solution, software acquisition follows requirements definition. Risk-management planning belongs to the later project-planning work.