QuestionQ562

Risk Response and Reporting

When presenting risk assessment results to senior management, which of the following is MOST important to include to support risk-based decision-making?

  • A A list of assets exposed to the highest risk
  • B Potential losses compared to treatment cost
  • C Recent audit and self-assessment results
  • D Risk action plans and associated owners
Explanation

Comparing potential losses with treatment costs provides the financial trade-off needed to determine whether risk treatment is justified and to prioritize risk responses.