Risk Response and Reporting

You are a Project Manager for Company Inc. and are assigning a risk response owner to carry out each agreed-upon and funded risk response. Which of the following processes are you performing?

  • A Quantitative Risk Analysis
  • B Identify Risks
  • C Plan risk response
  • D Qualitative Risk Analysis
Explanation

Plan Risk Responses develops actions to address project risks and assigns a risk response owner to implement each agreed-upon, funded response.