QuestionQ518

Risk Assessment

An organization has started a project to introduce an IT-based service to customers and capitalize on being first to market. Which of the following should be of GREATEST concern to senior management?

  • A The project is likely to deliver the product late.
  • B More time has been allotted for testing.
  • C A new project manager is handling the project.
  • D The cost of the project will exceed the allotted budget.
Explanation

First-to-market advantage depends primarily on delivering the service before competitors. A likely delay in product delivery directly jeopardizes that strategic objective.