QuestionQ489

Risk Assessment

You are a project manager at SoftTech Inc. and are working with project stakeholders to start the qualitative risk analysis process. Which of the following inputs are required for qualitative risk analysis in your project?

Each correct answer represents a complete solution.

Choose three
  • A Project scope statement
  • B Cost management plan
  • C Risk register
  • D Organizational process assets
Explanation

Qualitative risk analysis evaluates the probability and impact of risks already recorded in the risk register. The project scope statement supplies project context for assessing those risks, while organizational process assets can provide risk-rating definitions, templates, and lessons learned. A cost management plan is not a standard input to qualitative risk analysis.