Which of the following would BEST mitigate an identified risk scenario?

Explanation

Executing a risk response plan applies the chosen treatment to an identified risk, such as mitigating, avoiding, transferring, sharing, or accepting it. Risk mitigation is a subset of risk response and entails implementing risk-reducing controls or countermeasures.