QuestionQ240

Risk Response and Reporting

You and your project team are identifying risks that may occur within your project. Some are minor risks that would not significantly affect the project if they occurred. What should you do with these identified risk events?

  • A These risks can be dismissed.
  • B These risks can be accepted.
  • C These risks can be added to a low priority risk watch list.
  • D All risks must have a valid, documented risk response.
Explanation

Low-priority risks that do not warrant immediate response actions can be recorded on a watch list and monitored. This preserves awareness of them while focusing active risk-management effort on more significant risks.