QuestionQ220

Risk Response and Reporting

A control owner has chosen to implement a compensating control rather than the control selected in the risk action plan. After reassessing the risk, which action is MOST important for the risk practitioner?

  • A Notify senior management of the control owner's decision.
  • B Seek approval of the change from the risk owner.
  • C Update control ownership in the risk register.
  • D Update policies relevant to the risk.
Explanation

The risk owner is accountable for risk-based decisions and for selecting a response that brings residual risk within the organization’s accepted tolerance. Replacing a planned control with a compensating control changes the risk treatment, so the risk owner must approve that change after the reassessment.