QuestionQ198

Risk Assessment

You are the project manager for the TTP project and are performing the Identify Risks process. You must create the risk register. Which of the following items are included in the risk register?

Each correct answer represents a complete solution.

Choose two
  • A List of potential responses
  • B List of key stakeholders
  • C List of mitigation techniques
  • D List of identified risks
Explanation

The risk register records identified risks and may include potential responses for those risks. Risk mitigation is only one possible response strategy, whereas the register’s component is the broader list of potential responses.