QuestionQ1877

Risk Response and Reporting

Which risk-register element is MOST useful to share with key stakeholders to support informed decision-making?

  • A Threat source
  • B Risk owner
  • C Control owner
  • D Mitigation plan
Explanation

A mitigation plan identifies the actions intended to reduce or manage a risk. It gives stakeholders the information needed to evaluate the proposed response, its likely effectiveness, and any associated resource or decision needs.