QuestionQ1792

Risk Response and Reporting

Beth is a project team member on the JHG Project. Beth added extra project features, introducing new risks to the project work. The JHG Project manager chooses to remove the features Beth added. What is the process of removing the extra features to eliminate the risks called?

  • A Detective control
  • B Preventive control
  • C Corrective control
  • D Scope creep
Explanation

A corrective control addresses an identified undesirable condition by removing or remediating its cause. Eliminating the added features removes the source of the newly introduced project risks.

Community Discussion

No comments yet. Be the first to start the discussion!