QuestionQ1697

Risk Response and Reporting

You are serving as a project manager at Bluewell Inc. You are approaching the final stages of project execution and preparing for the last risk monitoring and control activities. For your project archives, which of the following is an output of risk monitoring and control?

  • A Qualitative risk analysis
  • B Risk audits
  • C Quantitative risk analysis
  • D Requested changes
Explanation

Risk monitoring and control can produce requested changes when responding to risks requires corrective action, preventive action, or changes to project plans and baselines. Risk audits are used to evaluate risk-management effectiveness, while qualitative and quantitative risk analysis are distinct analysis processes.