QuestionQ1639

Risk Response and Reporting

A program manager has completed an unsuccessful disaster recovery test. Which of the following should the risk practitioner recommend as the NEXT course of action?

  • A Identify what additional controls are needed
  • B Update the business impact analysis (BIA)
  • C Prioritize issues noted during the testing window
  • D Communicate test results to management
Explanation

Deficiencies identified during a failed disaster recovery test should be prioritized according to their impact and urgency. This establishes the order for remediation and supports an effective corrective-action plan.