QuestionQ1619

Risk Response and Reporting

When implementing an IT risk management program, at which of the following times is it BEST to evaluate the effectiveness of current controls?

  • A Before defining a framework
  • B During the risk assessment
  • C When evaluating risk response
  • D When updating the risk register
Explanation

Current control effectiveness must be evaluated during the risk assessment because existing controls affect the likelihood and impact of a risk scenario, and therefore its residual risk. That assessment informs the subsequent choice of risk response and related risk-register updates.