QuestionQ1567

Risk Assessment

You are the project manager for the RFT project. You have identified a risk that the enterprise’s IT system and application landscape is so complex that, within a few years, expanding capacity will be difficult and software maintenance will become very expensive. To address this risk, the adopted response is to re-architect the existing system and purchase a new integrated system. Under which of the following risk-prioritization options would this case be categorized?

  • A Deferrals
  • B Quick win
  • C Business case to be made
  • D Contagious risk
Explanation

A response involving re-architecting an existing system and purchasing a new integrated system requires substantial investment, planning, and justification of expected benefits. It is therefore categorized as a business case to be made.