QuestionQ150

Risk Response and Reporting

Which of the following is the MOST significant outcome of monitoring key risk indicators (KRIs)?

  • A Increased risk control efficiency
  • B Improvement of risk awareness
  • C Identification of risk event root causes
  • D Development of risk transfer strategies
Explanation

Key risk indicators provide early signals of increasing risk exposure, enabling stakeholders to recognize changes in the risk profile. Their principal outcome is therefore improved risk awareness; they do not primarily measure control efficiency, determine event root causes, or develop risk-transfer strategies.