QuestionQ1480
Risk Response and ReportingAn operations manager has requested risk acceptance after a mitigation plan has failed. Which of the following is the BEST response from the risk practitioner?
- A Ask the risk owner to review the request.
- B Document the risk acceptance in the risk register.
- C Reassess the risk scenario associated with the action plan.
- D Adjust the organization's risk profile by the amount of risk accepted.
Community Discussion