QuestionQ1442

Risk Response and Reporting

The BEST control for mitigating the risk associated with project scope creep is to:

  • A consult with senior management on a regular basis
  • B apply change management procedures
  • C ensure extensive user involvement
  • D deploy CASE tools in software development
Explanation

Formal change management procedures require proposed scope changes to be assessed, authorized, documented, and incorporated into the project plan in a controlled manner. This directly prevents uncontrolled expansion of project requirements.