QuestionQ1393

Risk Response and Reporting

Which of the following is management’s PRIMARY consideration when approving risk-response action plans?

  • A Prioritization for implementing the action plans
  • B Ability of the action plans to address multiple risk scenarios
  • C Ease of implementing the risk treatment solution
  • D Changes in residual risk after implementing the plans
Explanation

Risk-response action plans must reduce risk to a residual level that management is willing to accept. The post-treatment residual risk therefore determines whether the planned response is appropriate.