QuestionQ1369
Risk AssessmentYou are the project manager for your project and must analyze various project risks. You have chosen quantitative analysis rather than qualitative risk analysis.
What is the MOST significant drawback of using quantitative analysis instead of qualitative risk analysis?
- A lower objectivity
- B higher cost
- C higher reliance on skilled personnel
- D lower management buy-in
Community Discussion