QuestionQ1221
Risk Response and ReportingYou are the project manager for the NNN Project. Stakeholders in the two-year project requested that status reports be sent to them by email every week. You agreed and have sent the reports every Thursday. After six months of the project, the stakeholders are pleased with project progress and would like the status reports reduced to every two weeks. Which process will evaluate the change to this project process and implement it in the project?
- A Configuration management
- B Communications management
- C Perform integrated change control process
- D Project change control process